Unpopular opinion: My company's last-minute approvals hurt our work.

We rush jobs and quality suffers.
2 comments

Log in to join the discussion

Log In
2 Comments
baker.willow
Had the same problem with my old team. We started making a simple tracking doc showing exactly how many hours of rework each last-minute change caused. The numbers were ugly enough that our manager finally pushed back on the approval side. It didn't fix everything, but it forced them to give us timelines a day earlier, which was huge.
2
scott.morgan
Nice! Turn that into a weekly report they have to see.